INTRODUCTION
An award-holder of an arbitration which took place outside India
would be rendered remediless if prompt and effective interim
measures are not granted to the award-holder in the interregnum in
relation to the assets of the award-debtor which are located in
India.
The aforesaid was observed by hon'ble Justice Moushumi
Bhattacharya of the Calcutta High Court in the matter of Medima
LLC v. Balasore Alloys Limited,1 while deciding
upon the maintainability of an application for interim measures
[Relief Application] under Section 9 of the
Arbitration and Conciliation Act, 1996 [Act,
1996], post-award, in a foreign-seated arbitration. The
Calcutta High Court in the case also dealt with the applicability
of proviso to Section 2(2) of the Act, 1996 in order to
ascertain whether the intention of the parties to the agreement was
to exclude the recourse to Section 9 of the Act, 1996.