Roadway Solutions India Infra Limited vs National Highways Authority Of India

The Court confined the Section 9 proceedings to the Petitioner’s prayer seeking restraint against the Respondent from acting upon the Notice of Intention to Terminate dated 16.07.2026. It reiterated that Section 9 is protective in nature and aims to preserve the subject matter of arbitration and prevent the proceedings from becoming infructuous. Interim relief depends upon a prima facie case, balance of convenience and irreparable injury.

IndiaGovernment, Public Sector

FACTS

  1. The parties entered into a Contract dated 17.10.2022 for the execution of the highway project inter alia the original Scheduled Completion Date was 12.01.2025.
  2. Disputes arose regarding delay in execution. The Petitioner attributed the delay to the Respondent’s failure to provide Right of Way under Clause 8.1, non-availability of continuous work fronts and delays in obtaining approvals. The Respondent attributed the delay to the Petitioner’s failure to deploy adequate resources; maintain the highway stretch and comply with contractual and safety obligations.
  3. The Petitioner sought extension of time under Clause 10.5(ii), pursuant to which the Respondent’s Engineer recommended an extension of 474 days. The parties thereafter executed a Settlement Agreement dated 25.04.2025, revising the Scheduled Completion Date to 30.04.2026 and Milestone-III to 11.01.2026.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from