By a judgment dated 23-09-2024, the Supreme Court dismissed a civil appeal filed by Damodar Valley Corporation (DVC) challenging a judgment of the Appellate Tribunal...

IndiaEnergy and Natural Resources

By a judgment dated 23-09-2024, the Supreme Court dismissed a civil appeal filed by Damodar Valley Corporation1 (DVC) challenging a judgment of the Appellate Tribunal for Electricity (APTEL) dated 28-08-20242. Supreme Court effectively upheld the APTEL ruling to the effect that:

(i) All disputes which have a bearing on the tariff of a generating company or transmission licensee would constitute tariff disputes (be it change in law or delay in completion of projects or invocation of force majeure) and fall solely within the jurisdiction of the Central Electricity Regulatory Commission3 under Section 79(1)(f) of the Electricity Act, 2003 ("E Act").

(ii) Disputes relating to termination or breach of contract, and other disputes which do not impact the tariff, directly or indirectly, are non-tariff related disputes, which must be mandatorily referred to arbitration.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from