This decision emphasizes the object of the 2003 Act and the National Electricity Policy to promote renewable sources of energy.

IndiaEnergy and Natural Resources
Amitabh Sharma
Amitabh Sharma
Nishant Beniwal
Nishant Beniwal
Rahul Arora
Rahul Arora
Anjali Viswamohanan
Anjali Viswamohanan
Author LinkedIn connections

Recently, the Supreme Court of India (SC)1 upheld the validity of the Rajasthan Electricity Regulatory Commission (Renewable Energy Obligation) Regulations, 2007 (2007 Regulations) and the Rajasthan Electricity Regulatory Commission (Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) Regulations, 2010 (2010 Regulations) (together, the Regulations), with regard to the renewable energy purchase obligation (RPO) and the obligation to pay surcharge in the event of a shortfall in meeting the RPO imposed on captive generation power plants and other obligated entities.

The High Court of Rajasthan (High Court)2 had held that the Rajasthan Electricity Regulatory Commission (RERC) has been empowered to frame the Regulations in exercise of the powers conferred under Sections 61, 66, 86(1)(e) and 181 of the Electricity Act, 2003 (2003 Act) and that the Regulations do not contravene the provisions of the 2003 Act, Articles 14 and 19(1)(g) of the