The Hon'ble Supreme Court of India (“Supreme
Court”) in the case of Chamundeshwari
Electricity Supply Corporation Limited vs. Saisudhir Energy
(Chitradurga) Private Limited and Anr.1
set aside the judgment passed by Appellate Tribunal for Electricity
(“APTEL”)2 along with the
order of the Karnataka Electricity Regulatory Commission
(“KERC”).
Suppreme Court adjudicated on the issue related to extension of
commercial operation date (“COD”) of a
solar power developer due to delay in construction/completion of
evacuation system by a State Transmission Licensee which was cited
as ‘force majeure' by the developer.
Supreme Court held the developer must invoke the correct clause
of the Power Purchase Agreement
(“PPA”) to claim extension, and
omission to do so, including failure to issue a force majeure
notice, does not entitle any relief to the developer.