On 22 July 2020, the Ministry of Power (MoP) rolled out
Guidelines for Tariff Based Competitive Bidding Process for
Procurement of Round-The Clock Power from Grid Connected Renewable
Energy Power Projects, complemented with Power from Coal Based
Thermal Power Projects (Guidelines).
The Guidelines have been introduced, inter alia, to
provide for (i) supply of renewable energy along with the power
produced from coal based thermal power plants, to ensure
uninterrupted round the clock power supply to distribution
companies (DISCOMs); and (b) additional renewable energy capacity,
to ensure fulfilment of the renewable purchase obligation by
DISCOMs.
These Guidelines have been issued by MoP under Section 63 of the
Electricity Act 2003 (Electricity Act). Section 63 of the
Electricity Act provides for adoption of tariff by the appropriate
electricity regulatory commission, if such tariff has been
determined by a transparent bidding process under the
‘guidelines' issued by