Risk Allocation In India's 2025 Renewable Tenders (Curtailment, DSM, Change In Law And Performance Security)

In India's 2025 renewable tenders, risk is being re balanced more carefully between government procurers and private developers, especially around curtailment, deviation charges, change in law and execution security...

IndiaEnergy and Natural Resources

1. Introduction

In India's 2025 renewable tenders, risk is being re‑balanced more carefully between government procurers and private developers, especially around curtailment, deviation charges, change‑in‑law and execution security. Recent amendments to competitive bidding guidelines and tender documents show a clear attempt to make projects bankable while still protecting grid stability and public finances.

2. Core Risk themes in 2025 tenders

Recent bid documents for solar, wind and hybrid projects build on MNRE's (Ministry of New and Renewable Energy, the central ministry responsible for policy and promotion of renewable energy in India) "50 GW annual bidding trajectory" and updated tariff based competitive bidding guidelines. The Ministry of Power's 2025 proposals and amendments aim to improve clarity, standardise treatment of events like force majeure and change‑in‑law, and recalibrate performance‑security levels for different project types.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from