ARTICLE · 01 MAY 2020

Ministry Of New & Renewable Energy Provides Automatic Time Extension On Account Of Disruption Due To Lockdown As Force Majeure

Khaitan & Co.
Khaitan & Co.
Contributor
Khaitan & Co.

Khaitan & Co.

Founded in 1911, Khaitan & Co is a heritage law firm that has been a trusted adviser to leading...

View firm profile
Explore more from Khaitan & Co.

On 17 April 2020, Ministry of New & Renewable Energy, Government of India (MNRE) issued an office memorandum requiring all renewable energy implementing agencies to treat lockdown due to COVID-19 as ‘force majeure'.

IndiaEnergy and Natural Resources

On 17 April 2020, Ministry of New & Renewable Energy, Government of India (MNRE) issued an office memorandum (Memorandum II) requiring all renewable energy implementing agencies to treat lockdown due to COVID-19 as 'force majeure'.

The Memorandum has been issued in furtherance of MNRE's office memorandum dated 20 March 2020 (Memorandum I), which envisaged a framework for extension of scheduled commissioning dates of renewable energy projects considering disruption of supply chain due to COVID-19 as a force majeure event. Pursuant to Memorandum I, MNRE had, inter alia, directed: (a) all renewable energy implementing agencies of the MNRE such as Solar Energy Corporation of India Limited and NTPC Limited (Implementing Agencies) to treat delay on account of disruption of supply chain due to COVID-19, as force majeure; and (b) developers to submit formal application to the Implementing Agencies with documentary evidence in support of their claims.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this document does not necessarily reflect the views / position of Khaitan & Co but remain solely those of the author(s). For any further queries or follow up, please contact Khaitan & Co at [email protected].

See more popular content from