On 17 April 2020, Ministry of New & Renewable Energy,
Government of India (MNRE) issued an office memorandum (Memorandum
II) requiring all renewable energy implementing agencies to treat
lockdown due to COVID-19 as 'force majeure'.
The Memorandum has been issued in furtherance of MNRE's
office memorandum dated 20 March 2020 (Memorandum I), which
envisaged a framework for extension of scheduled commissioning
dates of renewable energy projects considering disruption of supply
chain due to COVID-19 as a force majeure event. Pursuant to
Memorandum I, MNRE had, inter alia, directed: (a) all
renewable energy implementing agencies of the MNRE such as Solar
Energy Corporation of India Limited and NTPC Limited (Implementing
Agencies) to treat delay on account of disruption of supply chain
due to COVID-19, as force majeure; and (b) developers to submit
formal application to the Implementing Agencies with documentary
evidence in support of their claims.