Share on LinkedInShare on LinkedIn

ARTICLE · 15 JANUARY 2020

KERC's Order In The Matter Of Hindustan Aeronautics Limited v. Bangalore Electricity Supply Company Limited And Karnataka Power Transmission Corporation Limited

The KERC has passed an order on December 17, 2019 in respect of how energy injected into the grid prior to the execution of a wheeling and banking is to be treated.

IndiaEnergy and Natural Resources

The KERC has passed an order on December 17, 2019 in respect of how energy injected into the grid prior to the execution of a wheeling and banking is to be treated.

Hindustan Aeronautics Limited which is the petitioner in the matter, is the owner of two wind projects with a capacity of 4.2 MW and 2.1 MW in the state of Karnataka. The petitioner had made an application for open access for the two wind projects to the State Load Despatch Centre. The wheeling and banking agreement(s) for the two projects were executed on 2 June, 2016. Between the date of commissioning of the wind projects and the date of execution of the wheeling and banking agreements, the petitioner had injected 49,17,902 units of electricity into the grid. While the petitioner contended that the injected power should be treated as banked energy, the respondents refused to pay for such power and treated it as infirm power.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from