Share on LinkedInShare on LinkedIn

ARTICLE · 02 DECEMBER 2025

Infrastructure, Projects And Energy Newsletter | August-October 2025

Dentons
Dentons
Contributor
Dentons

Dentons

The Firm Across over 80 countries, Dentons helps you grow, protect, operate and finance your...

View firm profile
Explore more from Dentons

We are pleased to present the third edition of the Infrastructure, Projects and Energy Newsletter.

IndiaEnergy and Natural Resources
Prashanth Sabeshan
Prashanth Sabeshan
Author LinkedIn connections

We are pleased to present the third edition of the Infrastructure, Projects and Energy Newsletter. This edition captures the major judicial pronouncements and key regulatory developments across the renewable energy, road, electricity, power, oil and gas sectors. Through this newsletter, we seek to highlight the shifting regulatory and legal frameworks and equipping stakeholders with strategic insights.

Judicial Pronouncements

Supreme Court Upholds Strict Enforcement of PPA Terms, Developers Cannot Cite State Transmission Utility Delays to Escape PPA Deadlines

A division bench of the Supreme Court ("SC"), in a judgment dated August 25, 2025, held that the terms of a Power Purchase Agreement ("PPA") must be strictly construed, and a power developer cannot be excused from its contractual obligations due to delays caused by a state-owned transmission utility, especially when the developer fails to invoke the specific remedies available in the contract.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from