The High Court of Delhi, through its judgment dated 22.06.2026 in Grew Energy Private Limited v. NTPC Renewable Energy Limited1 , held that where a specific provision governs a particular default, recourse must be had to such provision in preference to general provision.
NTPC Renewable Energy Limited (“NTPC”) had awarded contracts for supply of Solar PV Modules to Grew Energy Private Limited (“Grew”). Although Grew accepted the Notifications of Award, it failed to execute the formal contract agreement and furnish the Contract Performance Guarantee (“CPG”). Thereafter, NTPC inter alia terminated the awards, encashed the bid security, issued a fresh tender and suspended Grew from participating in future tenders for six months. Grew challenged the termination notice contending that, failure to execute the contract agreement or furnish the CPG only entitled NTPC to annul the awards and forfeit the bid security.