We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.
ARTICLE · 08 DECEMBER 2025
High Court Of Bombay Affirms That MERC Cannot Review MYT Order Without Notice And Opportunity Of Hearing To Affected Parties And Stakeholders.

Sagus Legal
Contributor

Sagus Legal
We are a full-service law firm providing comprehensive legal advisory and advocacy to clients. Our...
View firm profileThe High Court of Bombay through its judgement dated 03.11.2025 in O2 Renewable Energy VII Private Limited v. Maharashtra Electricity Regulatory Commission & Anr. , held that the Maharashtra Electricity Regulatory Commission cannot amend or review a MultiYear Tariff Order without providing an opportunity of hearing to all affected stakeholders.
IndiaEnergy and Natural Resources