The Hon’ble Central Electricity Regulatory Commission (“CERC” / “Commission”), vide Draft Order dated 06.05.20261 in Petition No. 11/SM/2026, has proposed a one-time regulatory framework for Renewable Energy (“RE”) generating stations which had obtained connectivity under the CERC (Connectivity and General Network Access to inter-State Transmission System) Regulations, 2022 (“GNA Regulations”) on the basis of Letters of Award (“LoAs”) issued by Renewable Energy Implementing Agencies (“REIAs”), only where the LoAs have not been culminated into Power Purchase Agreements (“PPAs”) within the prescribed period.
Accordingly, CERC invoking its powers under Regulations 41 and 42 of the GNA Regulations relating to “Power to Relax” and “Power to Remove Difficulty” and has proposed a one-time mechanism to address such stranded LoA-based connectivity. Under the proposed framework, entities having connectivity granted on the basis of LoAs, where PPAs have not been signed within 12 months from