CERC Held That Mere Construction Of Internal Pooling Substation Does Not Shift Delivery Point Of Energy Agreed Between The Parties

Sagus Legal
Sagus Legal
Contributor
Sagus Legal

Sagus Legal

We are a full-service law firm providing comprehensive legal advisory and advocacy to clients. Our...

View firm profile
Explore more from Sagus Legal

The dispute arose after SJVN claimed that under the RfS, Power Purchase Agreement (“PPA”), Implementation & Support Agreement (“ISA”), and connection agreements, the CTU substation has constituted the delivery point for energy supplied under the PPA.

IndiaEnergy and Natural Resources

The Central Electricity Regulatory Commission (“CERC”) through its judgement dated 06.03.2026 in the matter of SJVN Green Energy Limited v. Gujarat Urja Vikas Nigam Limited1 dismissed the petition of SJVN Green Energy Limited (“SJVN”) seeking a declaration that the delivery point for its 100 MW solar project at Raghanesda Solar Park was the 220 kV side of the CTU Khimnawas Substation. SJVN also sought directions to Gujarat SLDC to revise the State Energy Accounts and to Gujarat Urja Vikas Nigam Limited (“GUVNL”) to make payments on the basis of scheduled energy measured at that point.

The dispute arose after SJVN claimed that under the RfS, Power Purchase Agreement (“PPA”), Implementation & Support Agreement (“ISA”), and connection agreements, the CTU substation has constituted the delivery point for energy supplied under the PPA. However, Gujarat SLDC and GUVNL treated the delivery point as the GETCO periphery and prepared the State Energy Accounts after accounting for applicable

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from