The Central Electricity Regulatory Commission (“CERC”), by its order dated 14.08.2026 in Petition No. 5/SM/20261, has approved the procedure for levy of compensation charges permitting connectivity grantees additional time to achieve the milestones prescribed under the CERC (Connectivity and General Network Access to the inter-State Transmission System) Regulations, 2022 (“GNA Regulations”). The order follows the draft procedure issued on 15.04.2026 and the consultation process thereon, and has been passed in exercise of the powers of relaxation under Regulations 41 and 42 of the GNA Regulations.
Under the extant framework, an entity granted connectivity is required to achieve prescribed milestones relating to submission of land documents, achievement of financial closure and declaration of the commercial operation date (“COD”), failing which Regulations 11B and 24.6 of the GNA Regulations attract revocation of connectivity and encashment of connectivity bank guarantees.