The Central Electricity Regulatory Commission ("CERC") in the matters of M/s. Oyster Renewable Energy Private Limited and Anr. vs. Central Transmission Utility of India Limited and Avaada Energy Private Limited and Anr. vs. Central Transmission Utility of India Limited.

IndiaEnergy and Natural Resources

The Central Electricity Regulatory Commission ("CERC") in the matters of M/s. Oyster Renewable Energy Private Limited and Anr. vs. Central Transmission Utility of India Limited1 and Avaada Energy Private Limited and Anr. vs. Central Transmission Utility of India Limited2, directed the Central Transmission Utility of India Limited ("CTUIL") to accept land documents in the name of the subsidiary company which was implementing the project, for connectivity granted to the parent company, in order to meet the conditions subsequent under Regulation 11A(1)3 of the Central Electricity Regulatory Commission (Connectivity and General Network Access to the inter-State Transmission System) Regulations, 2022 ("GNA Regulations").

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from