APTEL by its judgment dated 10.07.2025 in a batch of appeals in the matter of Punjab Energy Development Agency v. Punjab State Electricity Regulatory Commission & Ors., held that State Electricity Regulatory Commission are empowered to issue directions to State Nodal Agencies such as the Punjab Energy Development Agency under Electricity Act, 2003.

IndiaEnergy and Natural Resources

APTEL by its judgment dated 10.07.2025 in a batch of appeals in the matter of Punjab Energy Development Agency v. Punjab State Electricity Regulatory Commission & Ors.1, held that State Electricity Regulatory Commission ("SECs") are empowered to issue directions to State Nodal Agencies such as the Punjab Energy Development Agency ("PEDA") under Electricity Act, 2003.

APTEL held that PEDA, despite not being a generating company or licensee, can be impleaded as a party in regulatory proceedings before the Punjab State Electricity Regulatory Commission ("PSERC") where PEDA plays a direct and substantial role in the renewable energy procurement process. This includes activities such as issuing Letters of Intent, securing performance guarantees, and executing implementation agreements with project developers.