Equity Must Yield To Law: No Claim, No Compensation

In a recent judgment in the case titled Universal Petro Chemicals Ltd. Vs. BP PLC and Ors., the Supreme Court, when considering an appeal relating to contractual disputes...

IndiaCorporate/Commercial Law

In a recent judgment in the case titled Universal Petro Chemicals Ltd. Vs. BP PLC and Ors.1, the Supreme Court, when considering an appeal relating to contractual disputes, refused to award Universal Petro Chemicals compensation in lieu of specific performance of a contract because the plaintiff did not claim for damages specifically in the plaint.

Facts of the case leading to the appeal:

Universal Petro Chemicals Ltd. (hereinafter referred to as the “Appellant“) entered into a collaboration agreement with a German company, Respondent No. 3, under which the Appellant was required to manufacture and market lubricants based on Aral's formulation in India. Subsequent to the Collaboration Agreement, necessary approvals were obtained from the Reserve Bank of India (RBI) under the Foreign Exchange Management Act, 1973 on November 25, 994 which were then incorporated in the Collaboration Agreement vide a supplementary agreement in1995.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from