In a recent judgment in the case titled Universal Petro
Chemicals Ltd. Vs. BP PLC and Ors.1, the
Supreme Court, when considering an appeal relating to contractual
disputes, refused to award Universal Petro Chemicals compensation
in lieu of specific performance of a contract because the plaintiff
did not claim for damages specifically in the plaint.
Facts of the case leading to the appeal:
Universal Petro Chemicals Ltd. (hereinafter referred to as the
“Appellant“) entered into a
collaboration agreement with a German company, Respondent No. 3,
under which the Appellant was required to manufacture and market
lubricants based on Aral's formulation in India. Subsequent
to the Collaboration Agreement, necessary approvals were obtained
from the Reserve Bank of India (RBI) under the Foreign Exchange
Management Act, 1973 on November 25, 994 which were then
incorporated in the Collaboration Agreement vide a supplementary
agreement in1995.