INTRODUCTION
The hon'ble Supreme Court of India in its judgment titled
South Eastern Coalfields Ltd. and Ors. Vs. S.
Kumar's Associates AKM (JV)1 examined
a challenge against the judgment dated 07.11.2012 (impugned
judgment) passed by the Chhattisgarh High Court, whereby
the Division Bench comprising of Justice Sanjay Kishan Kaul and
Justice Hemant Gupta (as His Lordships then were) delved upon the
important issue of whether a letter of intent amounts to a valid
contract.
BRIEF FACTS
South Eastern Coalfields Ltd. (Appellant No.
1), a government company, floated a tender for carrying
out certain mining works on 23.06.2009. S. Kumar's Associates
AKM (JV) (Respondent) was the successful bidder
and a Letter of Intent (hereinafter referred to as
LoI) was issued to it on 05.10.2009 for a total
work of Rs. 387.40 lakhs. In terms of the said LoI, the Respondent
was to mobilize equipment for executing works and commence the
works immediately. The other terms included