Regulation 261/2004: Flight Delay And Connecting Flights

On 12 October 2017, the Court of Appeal handed down its decision in the joined cases of Gahan v Emirates and Buckley and ors v Emirates [2017] EWCA Civ 1530.

GlobalTransport

On 12 October 2017, the Court of Appeal handed down its decision in the joined cases of Gahan v Emirates and Buckley and ors v Emirates [2017] EWCA Civ 1530. In both cases the passengers suffered delays at a connecting point and, consequently, on arrival at their final destination. They claimed compensation under Regulation 261/2004 (the "Regulation"), as applied by the Court of Justice of the European Union (the "CJEU") in Sturgeon v Condor [2009]. The Liverpool County Court, which heard both cases, came to a different conclusion in each case.

The principal issues on appeal were whether delays suffered by the passengers during the second leg of their respective journeys were compensable under the Regulation, whether there was jurisdiction under the Regulation and whether the right to compensation under the Regulation is, insofar as non-Community air carriers are concerned, excluded by virtue of the exclusive liability regime established under the Montreal Convention

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from