Time at large is a legal concept from the United Kingdom. In
essence, it is applied where the Court finds that a schedule has
been so disrupted that the contractor cannot be held to any
milestone or completion dates and delay damages are therefore not
collectable.
Although it would be fair to say that said legal verbiage or an
exact "Canadian" definition of the term has not been
embraced by Canadian courts, the underlying principles have been
considered and this article provides a brief overview of a few
examples where time at large has been applied in Canada.