Professional Indemnity Insurance - Nature Of Risk - Policy Does Not Respond Where Engineer Has Design Responsibility But Loss Was Caused By Negligent Performance Of Work

In a claim under a P. I. policy arising from construction work, it is necessary to identify whether the cause of the loss was negligence in the mandating of the technique for the performance of the work (a P. I. risk) or negligence in the manner in which that work technique was performed (a construction risk).

GlobalInsurance

Baulderstone Hornibrook Engineering Pty Ltd -v- Gordian Runoff Limited and Ors [2008] NSWCA 243 (9 October 2008)

In Brief

In a claim under a P. I. policy arising from construction work, it is necessary to identify whether the cause of the loss was negligence in the mandating of the technique for the performance of the work (a P. I. risk) or negligence in the manner in which that work technique was performed (a construction risk).

Background

BHE was the head contractor for the third runway construction at Sydney Airport. A dispute arose between the "Airport" and BHE about the adequacy of the construction of the reinforced earth walls forming the perimeter of the third runway and the adjacent area known as the Millstream Channel Diversion. After practical completion, subsidence of backfill behind the facing panels of the reinforced earth walls was discovered.