INTRODUCTION
The quest of the contracting parties to secure themselves
against breaching acts of the opposite contracting party led to the
conceptualization of "Liquidated Damages". Pertinently,
the contracting parties may agree to payment of a certain sum on
breach of the contract. This compensatory measure devised by the
contracting parties is recognized under Section 741 of
the Indian Contract Act, 1872 (Contract
Act), which prescribes for payment of a reasonable
sum to the non-defaulting party.
The reasonability of the amount named in the contract payable on
the occurrence of default, is reckoned from the terms of the
contract identifying such compensatory measure as "genuine
pre-estimation of loss to be suffered by non-defaulting party in
case of occurrence of default by another party". The
parties thus having pre-estimated the amount of compensation, the
same attains eligibility as 'reasonable' under Section 74
of the Contract Act.