Requirements For Structural Stability And Decommissioning Costs For Wind Turbines

A German court has ruled that decommissioning bonds for onshore wind turbines must cover both above-ground and underground installations, including pile foundations, with removal required even in water protection areas unless demonstrably disproportionate.

GermanyEnergy and Natural Resources

In a decision issued at the end of last year (OVG Niedersachsen, 12 December 2025 – 12 MS 43/24), the Higher Administrative Court of Lower Saxony (OVG Niedersachsen) commented on the requirements for decommissioning bonds (Rückbausicherheiten) to be provided for onshore wind turbines, as well as on the requirements for evidence of structural stability in permitting procedures for onshore wind turbines (Standsicherheitsnachweis). Both aspects are relevant in project development and, in also in a transaction context. We have therefore summarised below the court’s key statements.

Background: An environmental association brought legal proceedings against an emission control permit (permit under the Federal Emission Control Act, or Bundes-Immissionsschutzgesetz (BImSchG Permit)) for three onshore wind turbines. In addition to the amount of the decommissioning bond ordered in the BImSchG Permit, the association criticised, among other things, the requirements imposed with respect to the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from