ARTICLE · 20 APRIL 2026

From "First Come" To "First Ready": Germany's New Maturity-Based Grid Connection Process For BESS And Large-Scale Consumers

Herbert Smith Freehills Kramer LLP
Herbert Smith Freehills Kramer LLP
Contributor
Herbert Smith Freehills Kramer LLP

Herbert Smith Freehills Kramer LLP

We have one of the largest Southeast Asia international law practices, working across the region...

View firm profile
Explore more from Herbert Smith Freehills Kramer LLP

Germany’s framework for allocating transmission grid connections is undergoing a fundamental shift.

GermanyEnergy and Natural Resources

Background:

Germany’s framework for allocating transmission grid connections is undergoing a fundamental shift.

With effect from 1 April 2026, the four German transmission system operators (50Hertz, Amprion, TenneT and TransnetBW) have introduced a new, maturity-based procedure (the Reifegradverfahren) for the allocation of grid connection capacity for large-scale consumers and storage projects, including battery energy storage systems (BESS), data centres and electrolysers.

The reform marks a departure from the previously applied "first come, first served" (Windhundprinzip) approach, under which grid capacity was allocated in chronological order of application.

The change responds to a significant increase in grid connection requests in recent years, particularly from large-scale storage projects, which have far exceeded both available connection capacity and planning assumptions under the German network development plan. At the same time, the existing allocation model has

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.