On 27 August 2024, the Federal Ministry for Economic Affairs and
Climate Protection (BMWK) presented a draft law which aims to
transpose the European Directive on Electricity
Market Design ((EU) 2024/1711) into German law.
The draft bill provides for comprehensive amendments to both the
Energy Industry Act (EnWG) and the Renewable Energy Sources Act
(EEG) and covers the areas of grid connection procedures, energy
communities, energy supply and grid regulation.
1. New structured procedure for grid connection in accordance
with Section 17 EnWG
a) Binding deadlines for processing the grid connection
application
While a coordinated grid connection procedure has existed for
some time for renewable energy plants (Section 8 EEG) and for power
plants of 100 MW or more (KraftNAV), no specific requirements have
yet been set for other plants. There are currently long waiting
times for battery storage projects despite the privileged status
introduced with Solar Package