Share on LinkedInShare on LinkedIn

ARTICLE · 11 DECEMBER 2024

Amendment To The Energy Industry Act: Changes For Energy Supply Companies And Grid And System Operators

Taylor Wessing
Taylor Wessing
Contributor

Taylor Wessing

Founded in 1986 and formerly known as e|n|w|c Attorneys at Law, Taylor Wessing CEE today is the...

View firm profile
Explore more from Taylor Wessing

On 27 August 2024, the Federal Ministry for Economic Affairs and Climate Protection (BMWK) presented a draft law which aims to transpose the European Directive on Electricity Market Design ((EU)...

GermanyEnergy and Natural Resources

On 27 August 2024, the Federal Ministry for Economic Affairs and Climate Protection (BMWK) presented a draft law which aims to transpose the European Directive on Electricity Market Design ((EU) 2024/1711) into German law.

The draft bill provides for comprehensive amendments to both the Energy Industry Act (EnWG) and the Renewable Energy Sources Act (EEG) and covers the areas of grid connection procedures, energy communities, energy supply and grid regulation.

1. New structured procedure for grid connection in accordance with Section 17 EnWG

a) Binding deadlines for processing the grid connection application

While a coordinated grid connection procedure has existed for some time for renewable energy plants (Section 8 EEG) and for power plants of 100 MW or more (KraftNAV), no specific requirements have yet been set for other plants. There are currently long waiting times for battery storage projects despite the privileged status introduced with Solar Package

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from