Explore more from Taylor Wessing

On 15 July 2025, the Federal Court of Justice (BGH) ruled (case no. EnVR 1/24) that network operators in network connection procedures under the Energy Industry Act (EnWG) may demand a construction cost subsidy (BKZ) for battery storage systems (BESS) based on the performance price model.

GermanyEnergy and Natural Resources

On 15 July 2025, the Federal Court of Justice (BGH) ruled (case no. EnVR 1/24) that network operators in network connection procedures under the Energy Industry Act (EnWG) may demand a construction cost subsidy (BKZ) for battery storage systems (BESS) based on the performance price model (BGH press release; full text of the decision). In doing so, the BGH clarified the admissibility of this practice and removed any doubts as to the legality of a BKZ for battery storage systems. On 22 July 2025, the BGH also published the reasons for its decision.

Background to the decision

The question of whether to grant a construction cost subsidy is a key (cost) factor in the implementation of BESS projects. Depending on the connection capacity, the costs often run into the tens of millions, which is why the BGH's decision was eagerly awaited in the industry.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from