Update On Fit For 55 And REPowerEU – "Renewables Acceleration Areas" Gain Political Support

New EU legislation to decarbonise sectors across the economy is in the process of being finalised. As we start December, we look at latest progress.

European UnionCorporate/Commercial Law

New EU legislation to decarbonise sectors across the economy is in the process of being finalised. As we start December, we look at latest progress.

We initially summarised the Fit for 55 and REPowerEU packages here and here and checked in on progress last month here.

Renewable Energy Directive

REPowerEU included a proposal to speed up the permit-granting process for renewable energy projects, including by establishment of renewables "go-to areas" in which Member States would be required to ensure that the permit-granting process happens particularly swiftly. "Go-to areas" have appeared again as "renewables acceleration areas".

MEPs in the Industry, Energy and Research Committee have now voted to shorten the maximum period for the permit-granting process for new installations from 12 to nine months, if located in a "renewables acceleration area". The MEPs consider that, outside of these area, the process should not exceed 18 months. The new permit-granting

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This article contains a general summary of developments and is not a complete or definitive statement of the law. Specific legal advice should be obtained where appropriate.

See more popular content from