This article continues to discuss Legal Issues in Contracts for
Sale of Large-sized Complete Set Equipment. The
first part of this article was published on
Chinalawinsight on October 2011.
II. Delivery and Acceptance
Because large-sized complete set equipment are often composed of
multiple parts, it is customary for the manufacturing and delivery
of equipment to occur in conjunction with the assembly sequence.
Accordingly, there are multiple deliveries, installations and
inspections during the contract performance. The general procedures
are as follows:
A. Inspection
The first inspection of the equipment is usually an open-package
joint inspection conducted by both parties upon the arrival of the
equipment at the destination port. If the package appears intact,
yet after inspection the equipment is found damaged, defective,
short of quantity or not conforming to the quality standards and
specifications, the buyer is entitled to request the seller to
repair,