Share on LinkedInShare on LinkedIn

ARTICLE · 24 JUNE 2022

You Can Fight City Hall: Provincial Approval For Three Sisters Mountain Village Development Prevails Over Municipal Objections

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In Three Sisters Mountain Village Properties Ltd v Town of Canmore, the Alberta Land and Property Rights Tribunal (the Tribunal) held that the Three Sisters Village Area Structure Plan...

CanadaReal Estate and Construction

In Three Sisters Mountain Village Properties Ltd v Town of Canmore,1 the Alberta Land and Property Rights Tribunal (the Tribunal) held that the Three Sisters Village Area Structure Plan (the Three Sisters ASP) complied with an approval granted by the provincial Natural Resources Conservation Board (the NRCB). Pursuant to section 619 of the Municipal Government Act (MGA), the Town of Canmore (the Town) had no authority to deny approval for, or demand certain changes to, the Three Sisters ASP.

This case reaffirms the principle that a municipality cannot deny a development or other application consistent with a provincial regulator's prior approval or authorization. In this case, section 619 eliminated municipal discretion to refuse or change the Three Sisters ASP respecting matters already decided by the NRCB; however, the Town retained authority over matters not addressed by the NRCB.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from