Winter Work, Existing Conditions And Delay Penalties: Three Lessons From The Court Of Appeal

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

When a contractor's bid assumes summer construction but the project extends into winter due to delayed notice to proceed, who bears the financial risk? This Quebec Court of Appeal decision examines the boundaries of contractor assumptions at the bidding stage and establishes important limits on when penalty clauses become circumstantially abusive despite being contractually valid.

CanadaReal Estate and Construction

Can a contractor claim additional costs when the notice to proceed is delayed and the project extends into winter? In Nahtac Constructions inc. v. Ville de Montréal, 2026 QCCA 1240, the Court of Appeal reiterated that a contractor basing its price on certain assumptions must ensure that those assumptions are supported by the tender documents or have been properly verified before submitting a bid. However, the Court confirmed that a delay penalty clause cannot be applied blindly when its effect becomes disproportionate to the circumstances and the actual harm suffered.

This decision followed the trial judgment that we analyzed in a 2024 article. It clarified the risks each party assumes at the bidding stage and the limits that the courts place on the application of penalty clauses.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from