What To Expect As The Implementation Of Prompt Payment In Alberta Looms: The Final Countdown

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

The Alberta Prompt Payment and Construction Lien Act (the "Act") is set to be implemented on August 29, 2022. As this date approaches, we have some final notes on what businesses can expect as the...

CanadaReal Estate and Construction

The Alberta Prompt Payment and Construction Lien Act (the "Act") is set to be implemented on August 29, 2022. As this date approaches, we have some final notes on what businesses can expect as the Act comes into force. Our prior commentary on the changes can be found in this article.

This post provides supplemental commentary on the transitional provisions of the Act and, in particular, what owners, contractors and other parties on construction projects can expect both prior to and after August 29. In addition, we will provide an update with respect to the adjudication process to be introduced under the Act.

Transition provisions

The transition provision of the Act provides that contracts and subcontracts entered into on or after the coming into force of the Act must conform to the provisions of the new legislative framework.1 As a result, the "bright line" date to be aware of in this respect is August 29, 2022.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from