Unjust Enrichment: A Claim Of Last Resort?

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

Subcontractors and suppliers who don't register a claim for lien for unpaid supply of materials and services are missing out on a strong mechanism to recover money from those who benefitted from their supply.

CanadaReal Estate and Construction

This article first appeared in the April issue of the OCA's Construction Comment.

Subcontractors and suppliers who don't register a claim for lien for unpaid supply of materials and services are missing out on a strong mechanism to recover money from those who benefitted from their supply. While unjust enrichment is often pleaded in civil actions against contractors and owners, we don't often see a judgment founded on that cause of action.

Recently, the Ontario courts refreshed the unjust enrichment cause of action by confirming that the common law remedy exists to allow subcontractors and suppliers to obtain money owed on a project from the owner — despite the fact that no lien was registered and no contractual relationship existed with the owner.