Generally speaking, subcontractors' liens expire 45 days
from the date of last supply1. This is the key
deadline all subcontractors are looking at when waiting on
payment. When determining if they still have time to lien,
most subcontractors look to their time sheets to find out when
their workers were last on site, thinking that they are out of time
to lien if the last timesheet is dated more than 45 days ago.
Similarly, the owner and general contractor will often rely on
site records (including log books and time sheets) to determine
what subcontractors still have lien rights based on who was on site
within the last 45 days.
However, the recent decision from Justice DiTomaso in
Toronto Zenith Contracting Ltd. v. Fermar Paving
Ltd.2 is a reminder that the inquiry into
timeliness cannot stop with a review of site records. When
determining timeliness, a Court will look at the subcontract to
determine if off-site work performed after the last date on site
will be