The Haida decision represents the Supreme Court of Canada's
seminal discussion on the Crown's duty to consult with and
accommodate First Nations who claim Aboriginal rights or title, but
have yet to establish those rights or title in court or through
treaty. A recent decision of the BC Supreme Court indicates that,
ten years on, we are still muddling our way through the
aftermath.
Moulton Contracting Ltd. v. British Columbia concerned
various claims that the plaintiff logging contractor advanced
against the Province of British Columbia, the Fort Nelson First
Nation (the "Band"), and particular members of the Band.
The dispute concerned two Timber Sale Licenses (TSLs) that the
Province had awarded to the plaintiff, but that the plaintiff was
unable to harvest on account of a blockade that various Band
members erected upon an access road. The blockade reflected the
Band members' unhappiness over the Province's consultation
efforts with respect to a major amendment made