On August 29, 2022, the Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 (the "PPCLA") came into force. The PPCLA changed the law governing the construction industry in Alberta.

CanadaReal Estate and Construction

On August 29, 2022, the Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 (the "PPCLA") came into force. The PPCLA changed the law governing the construction industry in Alberta. One such change was the imposition of mandated timelines for payment of invoices. Whether or not these timelines render "pay-when-paid" clauses in contracts ineffective has been debated since the introduction of the PPCLA. "Pay-when-paid" clauses stipulate that a contractor will only pay a subcontractor's invoice upon receipt of payment from the owner.

In the recent Alberta Court of King's Bench decision in Canadian Pressure Testing Technologies Ltd v EllisDon Industrial Inc ("Canadian Pressure"), the Court dealt with a dispute where the services agreement between the parties was enacted prior to the PPCLA coming into force.1

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.