ARTICLE · 05 APRIL 2020

Suspension Of Limitation And Procedural Time Periods: Construction Lien Expiry Periods Are Suspended

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

McCarthy Tétrault LLP provides a broad range of legal services, delivering strategic and...

View firm profile
Explore more from McCarthy Tétrault

On Friday the Lieutenant Governor in Council made an order under s. 7.1 of the Emergency Management and Civil Protection Act suspending limitation periods and procedural time periods...

CanadaReal Estate and Construction

On Friday the Lieutenant Governor in Council made an order under s. 7.1 of the Emergency Management and Civil Protection Act  suspending limitation periods and procedural time periods (the "Suspension Order"). The suspension is retroactive to March 16, 2020 and continues for the "duration of the emergency". Per section 7.1(4) of the Emergency Management and Civil Protection Act , the maximum suspension period is 90 days but can be further renewed in certain circumstances.

Sections 31 and 36 of the Construction Act are referred to as "other limitation periods" as listed in the Schedule to the Limitations Act, 2002. These sections of the Construction Act establish the time periods to preserve and perfect a lien. Accordingly, in our view the Suspension Order suspends the running of the clock to preserve and perfect construction liens.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from