A series of recent decisions handed down by Québec courts have provided valuable insights into the consequences of a contractor's failure to comply with the claims procedure stipulated in the contract.

CanadaReal Estate and Construction

A series of recent decisions handed down by Québec courts have provided valuable insights into the consequences of a contractor's failure to comply with the claims procedure stipulated in the contract.

Although non-compliance with such a procedure is in principle fatal to the contractor's claim when the contractual terms used are clear and binding in the eyes of the court, some recent decisions have set exceptions to this principle.

Thus, as demonstrated by the below decisions, the courts have, in certain circumstances, awarded damages to a contractor despite their failure to comply with the contractual claims procedure when it has been shown that (1)the client has clearly waived this procedure; (2)the client has breached their obligation to inform or to cooperate with the contractor; or (3)the client has breached the duty to act in good faith.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from