Restoring The Balance Of Power: Addressing Abusive Claims Of Lien Under The BC Builders Lien Act

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

McCarthy Tétrault LLP provides a broad range of legal services, delivering strategic and...

View firm profile
Explore more from McCarthy Tétrault

Construction project stakeholders have an important new precedent to rely on when seeking to eliminate grossly inflated claims of lien quickly and efficiently.

CanadaReal Estate and Construction

Construction project stakeholders have an important new precedent to rely on when seeking to eliminate grossly inflated claims of lien quickly and efficiently. Darwin Construction (BC) Ltd. v. PC Urban Glenaire Holdings Ltd.1 ("Darwin Construction") marks the first reported instance that a court has cancelled an inflated claim of lien under section 25(2)(b) of the Builder Lien Act2(the "BLA") for abuse of process before the trial of the lien claimant's enforcement action.

While BC courts have been reluctant to use this statutory cancellation mechanism previously, this decision provides a persuasive authority for owners and others to discover the basis for claims of lien and have them removed where they are exaggerated and the amount unsubstantiated.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from