In public construction tenders, the integrity of the process must take precedence over the pursuit of the lowest price.

CanadaReal Estate and Construction

In public construction tenders, the integrity of the process must take precedence over the pursuit of the lowest price. A recent decision involving the City of Lévis (the "City") confirms this: the lowest bid may be rejected if it fails to meet an essential requirement at the time of submission.

This decision is a clear reminder to contractors that initial non-compliance of a tender can have serious consequences, including the loss of a contract.

How two missing wheels sparked a tendering dispute

On July19, 2022, the City issued a call for tenders for a snow removal contract in the Pintendre district. The specifications required bidders to have a six-wheel-drive grader for the duration of the contract.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from