Prompt Payments And Settlement Of Dispute In Construction: A New Framework You Need To Know About

BCF Business Law
BCF Business Law
Contributor
BCF Business Law

BCF Business Law

Firm Overview With more than 520 employees, including 270 professionals, BCF Business Law is the...

View firm profile
Explore more from BCF Business Law

Quebec's new regulation establishes a framework for prompt payments and expedited dispute settlements in public construction projects, introducing tight deadlines and cascading payment mechanisms. How will these mandatory timelines and fast-track processes transform payment dynamics and dispute resolution for contractors, subcontractors, and public bodies?

CanadaReal Estate and Construction

Key points to remember

Ultimately, this new system fundamentally transforms the dynamics of payments and dispute resolution in public construction projects. Its tight deadlines and presumptions of validity require greater discipline from all parties involved in the contractual chain. Keep these rules in mind to maximize your chances of success: 

  • Implement a rigorous monthly invoicing process and strictly adhere to the prescribed deadlines: the 25th of the month for subcontractors, the 1st of the following month for the general contractor, and the 21st of the month for the review of payment request by the project owner or their professionals. Do not let the rejection deadlines pass: a request that is not contested in a timely manner is deemed valid. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from