ARTICLE · 26 JANUARY 2023

Priority Contest Between Liens And Building Mortgages: Court Of Appeal Resolves Dispute Over Interpretation Of Section 78(2) Of The Construction Act

These contests arise whenever premises are sold in circumstances where the proceeds of sale are not sufficient to cover all liens and all mortgage balances. Part XI of the Construction Act...

CanadaReal Estate and Construction

Priority disputes are common between construction lien claimants and mortgagees when the owner of a construction project becomes insolvent.

These contests arise whenever premises are sold in circumstances where the proceeds of sale are not sufficient to cover all liens and all mortgage balances. Part XI of the Construction Act, R.S.O. 1990, c. C.30 (the "Construction Act") contains a comprehensive set of rules applicable to priority disputes.

On January 3rd, the Ontario Court of Appeal released its decision in BCIMC Construction Fund Corporation v. 33 Yorkville Residences Inc., 2023 ONCA 1. The Court heard and dismissed an appeal brought by certain lien claimants involving the statutory interpretation of one of these rules – section 78(2) of the Construction Act.1 Where multiple building mortgages are taken to finance a construction project, liens have priority over the aggregate of the building mortgages to the extent of any deficiency in the owner's holdbacks

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from