Pacer Construction Holdings Corporation V. Pacer Promec Energy Corporation, 2018 ABCA 113

Pacer Promec Energy Corporation and its affiliates (collectively, the "Debtors") were in the business of oilfield construction.

CanadaReal Estate and Construction

"Pacer Promec Energy Corporation and its affiliates (collectively, the "Debtors") were in the business of oilfield construction. In late 2014, the Debtors' business began to fail and they were placed into a receivership by order of the Court of Queen's Bench of Alberta. FTI Canada Consulting Inc. (the "Receiver") was appointed as Receiver.

Early in the receivership, the Receiver made the somewhat unusual decision to complete some of the very significant construction projects the Debtors were involved with. As a result, it was anticipated that the Receiver would potentially be subject to a large number of claims in addition to the usual prereceivership claims against the Debtors, all of which would need to be addressed in the receivership. As many of these claims would be pursuant to the Builders' Lien Act (Alberta) the Receiver would need to review both the validity and priority of the claims.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from