This article is an update to our December 2017 article, where some of the most significant substantive changes to the Construction Lien Act (the "CLA") are considered.

CanadaReal Estate and Construction

This article is an update to our December 2017 article, where some of the most significant substantive changes to the Construction Lien Act (the "CLA") are considered.

On December 12, 2017, Bill 142, the Construction Lien Amendment Act, 2017 ("Bill 142"), received Royal Assent and became law in Ontario. Bill 142 changes the CLA's name to the Construction Act and represents a thorough and intensive modernization of the CLA.

Coming into Force of Substantive Amendments

Although now law, the substantive amendments to the CLA (including the CLA's name change) have yet to come into force. The Ministry of the Attorney General ("MAG") advised this month that the amendments respecting the modernization of the lien and holdback rules will come into effect July 1, 2018.  Amendments respecting prompt payment and adjudication will come into effect October 1, 2019.