Ontario Divisional Court Dismisses Application For Judicial Review Of Adjudicator's Determination

The Ontario Divisional Court recently released a decision on an application for judicial review of an adjudicator's determination under the prompt payment provisions of the Construction Act.

CanadaReal Estate and Construction

The Ontario Divisional Court recently released a decision on an application for judicial review of an adjudicator's determination under the prompt payment provisions of the Construction Act.  The application was dismissed (without any consideration of the underlying merits of the application) because of the applicant's failure to obtain a stay of the adjudicator's determination or to make payment. The Divisional Court's decision is a cautionary tale and highlights the importance of compliance with both the prompt payment and adjudication provisions of the Construction Act. 

The underlying adjudication

The applicant, SOTA, retained Andrid Group to build a dental clinic in Vaughan. Andrid Group performed work and invoiced SOTA. SOTA did not dispute the invoices within 14 days of receipt, resulting in those invoices becoming due and payable pursuant to section 6.4 of the Construction Act.  When SOTA did not pay, Andrid Group commenced an adjudication under

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from