In late 2019, the Ontario construction industry welcomed several amendments to the Construction Act,[1] chief among them being the introduction of a prompt payment...

CanadaReal Estate and Construction

In late 2019, the Ontario construction industry welcomed several amendments to the Construction Act,1 chief among them being the introduction of a prompt payment and adjudication regime to circumvent costly and time-consuming litigation. The prompt payment and adjudication regime is designed to secure a reasonable interim payment direction, while leaving open the ability for parties to revisit the substantive issues in other litigation and adjudication proceedings.

An adjudicator's decision under the Construction Act is an interim binding decision, but it is not final. The Construction Act does not provide for an appeal of an adjudicator's decision, rather judicial review is provided only with leave of the Divisional Court.2

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.