Ontario Court Underlines The Evidence And Analysis Required To Establish Critical Path Delays

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

Who is responsible for delays in multi-party projects? What happens when there are multiple independent causes of delay in the same time period? How do courts determine if a delay impacts the critical path of the project schedule?

CanadaReal Estate and Construction

Who is responsible for delays in multi-party projects? What happens when there are multiple independent causes of delay in the same time period? How do courts determine if a delay impacts the critical path of the project schedule?

The Ontario Superior Court of Justice was faced with these issues in the recent case Schindler Elevator Corporation v Walsh Construction Company of Canada1 where several subcontractors, including Schindler Elevator Corporation ("Schindler"), had delayed the performance of their respective  contracts. These delays allegedly impacted the critical path of the Women's College Hospital Capital Redevelopment Project (the "WCH Project") led by Walsh Construction/Bondfield Partnership (Walsh Construction Company of Canada and Bondfield Constructed Company Limited, collectively "WBP").

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from