Ontario Court Of Appeal Affirms That Construction Liens' Priority Under The Construction Act Is Limited To Extent Of The Deficiency In The Owner's Holdback

The decision in BCIMC Construction Fund Corp. et al. v. 33 Yorkville Residences Inc. et al., involved a number of lien claimants which had provided services and materials to the owner of a condominium development.

CanadaReal Estate and Construction

BCIMC Construction Fund Corp. et al. v. 33 Yorkville Residences Inc. et al., 2023 ONCA 1 (CanLII)
The decision in BCIMC Construction Fund Corp. et al. v. 33 Yorkville Residences Inc. et al.1, involved a number of lien claimants which had provided services and materials to the owner of a condominium development. The owner of the condominium had become insolvent and the property subject to the improvement had sold by a Receiver pursuant to a court order. At the time of sale, there were six mortgages registered against the property and two were building mortgages pursuant to Section 78(2) of the Construction Act.2The parties did not dispute that the lien claimants are entitled to a priority payment out of the proceeds of sale to the extent of any deficiency in the owner's holdback under Section 22(1) of the Construction Act. The issue in dispute was the distribution priority pursuant to Section 78(2) of the Construction Act, which outlines the method in determining the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from