Ontario Court Of Appeal: A Debtor's Assurances May Prolong The Discoverability Of A Creditor's Claim For Non-Payment

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

Understanding limitation periods are of crucial importance in the construction industry, particularly when a contractor is faced with unpaid invoices for services or materials rendered.

CanadaReal Estate and Construction

Understanding limitation periods are of crucial importance in the construction industry, particularly when a contractor is faced with unpaid invoices for services or materials rendered. The Ontario Court of Appeal stepped back into the spotlight in this regard with its decision in Thermal Exchange Service Inc. v Metropolitan Toronto Condominium Corporation No. 1289, 2022 ONCA 186, in holding that a defendant's assurances may prolong the "discoverability" of a claim for non-payment.

Background

The respondent on appeal, Thermal Exchange Service Inc. ("Thermal Exchange"), serviced HVAC units for 13 years as requested by the appellant, Metropolitan Condo Corporation (the "Condo Corp."). Each work order invoice required payment from the Condo Corp. within 30 days. However, the Condo Corp. typically delivered late payment, oftentimes some 300 days late. Despite the late payments, Thermal Exchange continued to perform the requested work orders.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from