One Remedy Or More? The Supreme Court Of Canada Clarifies Contractors' Rights Under Builders' Lien Legislation

On September 18, 2015, the Supreme Court of Canada issued its reasons in Stuart Olson Dominion Construction Ltd. v. Structal Heavy Steel, 2015 SCC 43.

CanadaReal Estate and Construction

On September 18, 2015, the Supreme Court of Canada issued its reasons in Stuart Olson Dominion Construction Ltd. v. Structal Heavy Steel, 2015 SCC 43. Although the judgment concerned the interpretation of the Manitoba Builders' Lien Act, it has implications for owners, contractors and others in the construction industry across Canada, including remedies available to industry participants in British Columbia under the BC Builders Lien Act. The decision will no doubt have an important procedural impact on how liens ought to be discharged during the currency of a project where the claim is disputed.

The facts of the case were rather unremarkable. A dispute arose between a contractor and subcontractor on the construction of a stadium at the University of Manitoba. The dispute was not resolved and the subcontractor filed a claim of builders' lien. In order to ensure funds did not cease to flow on the project, the contractor secured the discharge of the lien by posting a

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from